April 2017
Related Article:
Hot Construction Market Shows No Signs of Slowing
Click below for earlier editions:
2015
Rank |
Project/Location |
Project Costs ($ Mil.) |
Start/End Dates |
老板 |
Team |
---|---|---|---|---|---|
1 |
LOS ANGELES STADIUM AT HOLLYWOOD PARK
Inglewood, Calif. |
$2,600 |
Nov. 2016 Aug. 2019 |
Hollywood Park Land Co.
|
Designer:HKS Inc. Contractor:Turner/AECOM |
2 |
CENTURY PLAZA REDEVELOPMENT
Century City, Calif. |
$2,500 |
Dec. 2016 March 2019 |
Woodridge Capital LLC
|
Designer:Pei Cobb Freed & Partners; Gensler; HED Architects Contractor:Webcor Builders |
3 |
MID-COAST走廊交通项目
San Diego |
$1,700 |
Fall 2016 2021 |
SANDAG-Contracts & Procurement
|
CM/GC:Mid-Coast Transit Constructors, a Joint Venture of Stacy & Witbeck Inc., Skanska USA and Herzog Contracting Corp. |
4 |
OCEANWIDE CENTER
San Francisco |
$1,600 |
Dec. 2016 2021 |
Oceanwide Holdings
|
Designer:Foster + Partners; Heller Manus Architects Contractor:Swinerton/Webcor JV |
5 |
LLUMC CAMPUS TRANSFORMATION PROJECT
Loma Linda, Calif. |
$1,400 |
Spring 2016 2020 |
Loma Linda University
|
Designer:NBBJ Contractor:McCarthy Building Cos. |
6 |
CHEVRON RICHMOND REFINERY MODERNIZATION
Richmond, Calif. |
$985 |
Dec. 2016 Dec. 2018 |
Chevron Richmond
|
EPC:Chevron Richmond |
7 |
CALIFORNIA FLATS SOLAR POWER FACILITY
Monterey County, Calif. |
$850 |
Jan. 2016 2018 |
California Flats Solar LLC
|
Designer:First Solar Inc. Contractor:McCarthy Building Cos. |
8 |
MARIN GENERAL HOSPITAL REPLACEMENT
Greenbrae, Calif. |
$535 |
July 2016 Mid-2020 |
Marin Healthcare District
|
Designer:Lee Burkhart Liu Inc./Perkins Eastman Contractor:McCarthy Building Cos. |
9 |
NEW LONG BEACH CIVIC CENTER
Long Beach, Calif. |
$520 |
July 2016 2019 |
Plenary-Edgemoor Civic Partners; City of Long Beach
|
Designer:SOM | Skidmore,Owings & Merrill LLP Contractor:Clark Construction Group |
10 |
BEVERLY CENTER RENOVATION
Los Angeles |
$500 |
March 2016 Late 2018 |
Taubman Co.
|
Designer:Massimiliano Fuksas Architetto Contractor:Jacobsen/Swinerton Construction |
10 |
MEXICAN MUSEUM AND RESIDENTIAL TOWER
San Francisco |
$500 |
March 2016 March 2019 |
The Mexican Museum
|
Designer:Handel & Associates Architects Contractor:Webcor Builders |
10 |
STAR WARS LAND DISNEYLAND
Anaheim |
$500 |
April 2016 2019 |
Walt Disney Co.
|
Designer:Walt Disney Imagineering Contractor:Whiting-Turner Contracting Co. |
13 |
SAN FRANCISCO INTERNATIONAL AIRPORT TERMINAL 1 BOARDING AREA B RECONSTRUCTION
San Francisco |
$477 |
Dec. 2016 July 2020 |
City & County of San Francisco Airports Commission
|
Designer:Gensler Contractor:Austin Webcor JV |
14 |
TRANSBAY 8
San Francisco |
$465 |
Aug. 2016 Feb. 2020 |
因为有关。的California
|
Designer:OMA/Rem Koolhaas and Fougeron Architecture Contractor:Webcor Builders |
15 |
CALIFORNIA HIGH-SPEED RAIL CONSTRUCTION PACKAGE 4
Kern & Tulare Counties, Calif. |
$444 |
Sept. 2016 June 2019 |
California High Speed Rail Authority
|
Design-Build:California Rail Builders LLC |
16 |
SAN FRANCISCO INTERNATIONAL AIRPORT TERMINAL 1 CENTER RENOVATION
San Francisco |
$442 |
Sept. 2016 Late 2022 |
City & County of San Francisco Airports Commission
|
Designer:Gensler Contractor:Hensel Phelps Construction Co. |
17 |
ECHOWATER BIOLOGICAL NUTRIENT REMOVAL/ PRIMARY EFFLUENT PUMPING STATION
Elk Grove, Calif. |
$415 |
Aug. 2016 May 2021 |
County of Sacramento
|
Designer:Black & Veatch (BNR); CH2M (PEPS) Contractor:Dragados USA Inc. |
18 |
1120 S GRAND SOUTH PARK PHASE 2
Los Angeles |
$375 |
Aug. 2016 2019 |
Mack Urban; AECOM
|
Designer:A.C. Martin/Togawa Smith Martin Contractor:Tishman Construction Corp. |
19 |
KAHULUI AIRPORT CONSOLIDATED CAR RENTAL FACILITY
Kahului, Hawaii |
$340 |
April 2016 Late 2019 |
Dept. of Transportation - Airports Division
|
Designer:Demattei Wong Architecture Contractor:Hawaiian Dredging Construction Co. |
20 |
MOFFETT TOWERS II
Sunnyvale, Calif. |
$338 |
Aug. 2016 Q3 2018 |
Jay Paul Co.
|
Designer:DES Architects + Engineers Contractor:Level 10 Construction |
21 |
HONOLULU AIRPORT CONSOLIDATED CAR RENTAL FACILITY
Honolulu |
$315 |
Oct. 2016 2020 |
State of Hawaii Dept. of Transportation
|
Designer:Demattei Wong Architecture Inc. Contractor:Watts Constructors |
22 |
SPRING STREET TOWERS
Los Angeles |
$305 |
Jan. 2016 June 2018 |
Holland Partner Group; North American Sekisui House LLC
|
Designer:MVE + Partners Contractor:Holland Construction |
23 |
200-MW TULE WIND POWER PROJECT
Boulevard, Calif. |
$300 |
Oct. 2016 Late 2017 |
Avangrid Renewables
|
Designer:Avangrid Renewables Contractor:Tule Wind LLC |
23 |
ONNI RESIDENTIAL TOWER
Los Angeles |
$300 |
April 2016 May 2018 |
ONNI Group
|
Designer:Chris Dikeakos Architects Inc. Contractor:ONNI Group |
23 |
SANTA CLARA SQUARE APARTMENTS
Santa Clara, Calif. |
$300 |
Dec. 2016 2020 |
The Irvine Co.
|
Designer:MVE + Partners Contractor:Western National Contractors |
26 |
I-5 NORTH COAST EXPRESS LANES PROJECT
San Diego County |
$298 |
Nov. 2016 2020 |
SANDAG - Contracts & Procurement
|
Design-Build:Flatiron-Skanska-Stacy and Witbeck, a Joint Venture |
27 |
PECHANGA RESORT & CASINO EXPANSION
Temecula, Calif. |
$285 |
Jan. 2016 Dec. 2017 |
Pechanga Band of Luiseno Indians
|
Designer:Delawie Contractor:Tutor Perini Building Corp. |
28 |
160 FOLSOM
San Francisco |
$270 |
Late 2016 Late 2019 |
Tishman Speyer Properties
|
Designer:Studio Gang Architects Contractor:Lendlease |
29 |
FIVE LAGUNAS RESIDENTIAL COMPLEX
Laguna Hills, Calif. |
$260 |
Aug. 2016 Summer 2018 |
Merlone Geier Partners
|
Designer:Architects Orange Contractor:C.W. Driver |
30 |
STANFORD CHEM-H AND NEUROSCIENCES INSTITUTE BUILDING
Palo Alto, Calif. |
$252 |
Fall 2017 April 2019 |
Stanford University
|
Designer:Ennead Architects Contractor:Whiting-Turner |
Copyright ©2022. All Rights Reserved BNP Media.
Design, CMS, Hosting & Web Development ::ePublishing