April 2017
Related Article:
Power Plants, Hospitals Drive ENR MidAtlantic Top Starts
Click below for earlier editions:
2015|2014
Rank |
Project/Location |
Project Costs ($ Mil.) |
Start/End Dates |
Owner |
Team |
---|---|---|---|---|---|
1 |
GREENSVILLE COUNTY POWER STATION
Emporia, Va. |
$1,300 |
Dec. 2016 Dec. 2018 |
Dominion Virginia Power
|
GCFluor DesignerFluor |
2 |
LACKAWANNA ENERGY CENTER
Jessup, Pa. |
$1,200 |
April 2016 2018 |
Invenergy LLC
|
GCKiewit Corp. DesignerKiewit Corp. |
3 |
CAITHNESS MOXIE FREEDOM POWER PLANT
Salem Township, Pa. |
$900 |
Jan. 2016 May 2018 |
Moxie Energy
|
GCGemma Power Systems |
4 |
TENASKA WESTMORELAND COUNTY GENERATING STATION
Westmoreland County, Pa. |
$780 |
April 2016 Dec. 2018 |
坦Pennsylvania Partners LLC
|
GCBlack & Veatch |
5 |
WASHINGTON ADVENTIST HOSPITAL
White Oak, Md. |
$331 |
Dec. 2016 May 2019 |
Adventist HealthCare
|
GCTurner Construction Co. DesignerCallisonRTKL |
6 |
BAYHEALTH MEDICAL CAMPUS
Milford, Del. |
$300 |
May 2016 2018年秋季 |
Bayhealth Medical Center
|
GCWhiting-Turner Contracting Co. DesignerCannonDesigner |
6 |
655 NEW YORK AVE. OFFICE BUILDING
Washington, D.C. |
$300 |
Feb. 2016 June 2018 |
Douglas Development
|
GCDAVIS Construction DesignerShalom Baranes Associates |
8 |
THE BORO AT TYSONS-PHASE 1 RESIDENTIAL/RETAIL
Tysons Corner, Va. |
$262.5 |
June 2016 Sept. 2018 |
Lincoln Property Co.
|
GCClark Construction LLC DesignerFXFowle Architects |
9 |
PROCTER & GAMBLE MANUFACTURING FACILITY (2 PHASES)
Martinsburg, W.Va. |
$250 |
Oct. 2016 2019 |
Procter & Gamble Co.
|
DesignerFluor Federal Solutions |
10 |
COLUMBIA PLACE HOTELS & MULTIFAMILY RESIDENTIAL
Washington, D.C. |
$230 |
April 2016 Nov. 2018 |
Square 369 Hotel LLC
|
GCHensel Phelps Construction Co. DesignerCooper Carry Inc.; TVS Designer |
11 |
EISENHOWER EAST APARTMENT DEVELOPMENT
Alexandria, Va. |
$228 |
Nov. 2016 N/A |
Rushmark Properties
|
GCHitt Contracting DesignerHord Coplan Macht LLC |
12 |
FOUR CONSTITUTION SQUARE OFFICE BUILDING
Washington, D.C. |
$220 |
Dec. 2016 Dec. 2018 |
StonebridgeCarras
|
GCBalfour Beatty Construction D.C. DesignerHOK |
13 |
BRYN MAWR HOSPITAL (EXPANSION/RENOVATIONS)
Bryn Mawr, Pa. |
$200 |
July 2016 Feb. 2019 |
Main Line Health
|
GCHSC Builders & Construction Manager DesignerStantec; RTKL; Ballinger |
13 |
CAPITOL CROSSING
Washington, D.C. |
$200 |
March 2016 Jan. 2020 |
Property Group Partners
|
GCBalfour Beatty Construction D.C. DesignerSkidmore, Owings & Merrill; LERA Consulting Engineers; ECS |
13 |
FANNIE MAE OFFICE BUILDING
Washington, D.C. |
$200 |
April 2016 June 2018 |
Carr Properties
|
GCClark Construction DesignerWDG Architecture LLC |
13 |
300 M STREET N.E.
Washington, D.C. |
$200 |
March 2016 2017 |
The Wilkes Co.
|
DesignerHickok - Cole Architects |
13 |
MARYLAND LIVE CASINO
Hanover, Md. |
$200 |
Sept. 2016 2018 |
Cordish Cos.
|
GCTutor Perini Building Corp. DesignerKlai Juba Architects |
13 |
TRANSCONTINENTAL GAS PIPE LINE VIRGINIA SOUTHSIDE PROJECT II
Various Locations |
$200 |
Oct. 2016 2018 |
Williams Partners LLP
|
GCSunland Construction |
19 |
SENTARA NORFOLK GENERAL HOSPITAL (EXPANSION)
Norfolk, Va. |
$199 |
April 2016 June 2020 |
Sentara Healthcare
|
GCWhiting-Turner Contracting Co. DesignerHDR Architecture Inc. |
20 |
PHILADELPHIA MUSEUM OF ART (RENOVATION/ EXPANSION)
Philadelphia |
$196 |
Oct. 2016 Spring 2020 |
Philadelphia Museum of Art
|
GCLF Driscoll Co. LLC DesignerFrank Gehry |
21 |
I-64 CAPACITY IMPROVEMENT SEGMENT II
Newport News, Va. |
$190 |
Jan. 2016 May 2019 |
Virginia Dept. of Transportation
|
GCAllan Myers DesignerRinker Designer Associates; KCI Technologies |
22 |
FASHION OUTLETS PHILADELPHIA
Philadelphia |
$172.8 |
2016 2018 |
PREIT/Macerich Joint Venture
|
GCShoemaker-Skanska, a Joint Venture DesignerJPRA Architects |
23 |
UNIVERSITY AT SHADY GROVE - BIOMEDICAL SCIENCES & ENGINEERING EDUCATION FACILITY
Rockville, Md. |
$163 |
June 2016 Jan. 2019 |
University of Maryland Construction & Facilities
|
GCGilbane Building Co. DesignerCooper Carry & Associates Inc.; Lake/Flato |
24 |
MD. 404 WIDENING PROJECT
Maryland |
$161 |
Oct. 2016 Spring 2018 |
Maryland Dept. of Transportation
|
GC404 Corridor Safety Constructors - a Joint Venture of Wagman Heavy Civil, David A. Bramble and Allan Myers |
24 |
TYSONS CENTRAL RESIDENCES BUILDING F
Tysons Corner, Va. |
$161 |
Nov. 2016 Dec. 2018 |
Lennar Multifamily Community
|
GCHoar Construction DesignerDavis, Carter, Scott |
26 |
414 LIGHT STREET APARTMENTS
Baltimore |
160美元 |
March 2016 March 2018 |
Questar Properties Inc.
|
GCLend Lease Inc. DesignerSolomon Cordwell Buenz & Associates Inc. |
26 |
RAGINGWIRE DATA CENTER - VA3
Ashburn, Va. |
160美元 |
Dec. 2016 Dec. 2017 |
RagingWire
|
GCHolder DesignerIDGroup |
26 |
SUNBURY PIPELINE (MARCELLUS & UTICA SHALE REGION)
Shamokin Dam, Pa. |
160美元 |
Aug. 2016 Early 2018 |
UGI Energy Services LLC
|
GCUGI Sunbury LLC |
29 |
A.I. DUPONT HOSPITAL FOR CHILDREN INFRASTRUCTURE MASTER PLAN
Wilmington, Del. |
$150 |
Jan. 2016 Dec. 2021 |
Nemours
|
GCHSC Builders & Construction Managers DesignerBard, Rao & Athanas Engineers; Ewing Cole |
29 |
EAST HALLS RENOVATION AND NEW RESIDENCE HALL
University Park, Pa. |
$150 |
March 2016 2018年秋季 |
Penn State University-Office of Physical Plant
|
DesignerMackey Mitchell Associates |
29 |
901 H STREET N.E. BUILDING
Washington, D.C. |
$150 |
Nov. 2016 May 2019 |
WC Smith Co.
|
GCWCS Construction Co. DesignerTorti Gallas and Partners |
29 |
JOHNSON CONTROLS SHREWSBURY DEVELOPMENT CENTER
Shrewsbury, Pa. |
$150 |
Jan. 2016 June 2018 |
Johnson Controls Inc.
|
GCMcCarthy Building Cos. DesignerIDC Architects (Div. of CH2M Hill) |
29 |
NOVA PLACE
Pittsburgh |
$150 |
June 2016 June 2017 |
Faros Properties
|
GCFaros Construction; PJ Dick; Turner Construction; Rycon Construction; Zeus Construction; Frontier Construction DesignerDesmone Architects; Perkins Eastman; Piper O’Brien Herr; Strada; Stantec |
34 |
SECURE ADMINISTRATION/OPERATIONS FACILITY
Fort Belvoir, Va. |
$149.9 |
June 2016 May 2019 |
U.S. Army Corps of Engineers - Baltimore District
|
GCManhattan Construction Co. DesignerUSACE - Baltimore District |
35 |
FOREIGN AFFAIRS SECURITY TRAINING CENTER
Blackstone, Va. |
$145 |
Feb. 2016 N/A |
Allegheny Service Center (3PK)
|
GCM.A. Mortenson Construction DesignerKieran Timberlake Associates LLP |
36 |
BRENDAN IRIBE CENTER FOR COMPUTER SCIENCE & INNOVATION
College Park, Md. |
$142.5 |
June 2016 July 2018 |
University of Maryland Construction & Facilities
|
GCWhiting-Turner Contracting Co. DesignerHDR Architecture Inc. |
37 |
UNIVERSITY HOSPITAL EXPANSION
Charlottesville, Va. |
$142 |
Aug. 2016 2020 |
University of Virginia
|
GCSkanska DesignerPerkins & Will |
38 |
CITYCENTERDC CONRAD HOTEL - RETAIL (PHASE 2)
Washington, D.C. |
$140 |
Aug. 2016 March 2019 |
Bundy Development Corp.
|
GCTurner Construction Co. DesignerHerzog & De Meuron Architects |
39 |
DEPT. OF HOMELAND SECURITY CONSOLIDATION PHASE 2 - HISTORIC CENTER BUILDING
Washington, D.C. |
$139 |
March 2016 June 2019 |
U.S. General Services Administration
|
GCGrunley Construction Co. DesignerGoody Clancy; HDR; Shalom Baranes Associates |
40 |
CITY OF READING (FRITZ’S ISLAND) WASTEWATER TREATMENT PLANT RECONSTRUCTION
Reading, Pa. |
$137 |
Dec. 2016 N/A |
City of Reading
|
GCMichael F. Ronca & Sons Inc. DesignerRummel, Klepper & Kahl |
41 |
PENTAGON CENTRE RESIDENTIAL BUILDING A
Arlington, Va. |
$133 |
Dec. 2016 N/A |
Kimco Realty
|
GCWhiting-Turner Contracting Co. DesignerUrban Robot Associates |
42 |
SHAPIRO RESIDENCES AT UNION MARKET SOUTH
Washington, D.C. |
$130 |
Oct. 2016 Dec. 2018 |
Level 2 Development
|
DesignerShalom Baranes Associates |
43 |
海军联邦信用合作社
Vienna, Va. |
$127 |
July 2016 Late 2017 |
Navy Federal Credit Union
|
GCGilbane Building Co. DesignerJ3 Designer Collective Inc. |
44 |
UNION PLACE MIXED USE DEVELOPMENT - PHASE II
Washington, D.C. |
$125 |
Aug. 2016 N/A |
Toll Brothers Inc.
|
GCADC Builders Inc. DesignerDCS Architects |
45 |
纪念医院(替换)
York, Pa. |
$120 |
June 2016 Dec. 2017 |
Community Health System
|
GCThe Robins & Morton Group DesignerESA Earl Swensson Associates |
46 |
ONE LIGHT STREET-BALTIMORE
Baltimore |
$117.4 |
June 2016 Dec. 2018 |
MadisonMarquette/ Metropolitan Partnership
|
GCDonohoe DesignerAECOM DC |
47 |
STATE COLLEGE AREA SD HIGH SCHOOL (ADDITION/ RENOVATION)
State College, Pa. |
$117 |
Jan. 2016 July 2019 |
State College Area School District
|
GCLobar Inc. DesignerCrabtree Rohrbaugh & Associates Inc. |
48 |
THE ALTAIRE
Arlington, Va. |
$116 |
Oct. 2016 Aug. 2018 |
LCOR Inc.
|
GCBalfour Beatty Construction DesignerSK&I Architectural Designer Group |
49 |
RESA AT TYBER PLACE
District of Columbia |
$112 |
Nov. 2016 Aug. 2018 |
Skanska USA Commercial Development
|
GCSkanska Designer DesignerCollective Architects Inc. |
50 |
STUDENT HOUSING COMMUNITY
Pittsburgh |
$106 |
Aug. 2016 July 2018 |
Education Realty Trust
|
GCMassaro Corp. DesignerHumphreys & Partners Architects L.P. |