Quirk Hotel
里士满
Best Project


OwnerQuirk Hospitality LLC
领先设计公司3north Architects
General ContractorW.M. Jordan Co.
Civil EngineerTimmons Group
结构工程师Silman
MEP EngineerBass, Nixon & Kennedy


To meld history with modernity, the $15.7-million Quirk Hotel project required the adaptive reuse of two adjacent buildings in Richmond’s art district.

Building 201, which was constructed in 1916 as a department store, was rehabilitated; building 207 was converted to an art gallery. Building 207 was gutted, leaving a brick shell and upper windows facing Broad Street and an alley. Two new structures were constructed in the front and back of the shell to house the art gallery in the front and kitchen and loading area in the rear. An open-air court was created in the middle of 207, which is accessible from building 201’s lobby floor. Guest rooms line a double-loaded corridor in the floors above, reusing the existing windows along Jefferson and Broad streets. New windows along the west facade overlook a courtyard.

A penthouse level was added to the roof of 201 to create a single-loaded corridor of rooms with large terraces set back on all sides. The penthouse and rooftop bar levels in 201 increased the building’s wind load requirements. The existing structure could not withstand wind loads in conformity with the current building code so the team built a steel bracing system in 207 to provide wind bracing to 201. Most of this support is hidden in the walls, but some X-braces were left exposed in the art gallery as an architectural statement.

The owner used state and federal historic tax credits, which drove changes that continued through construction. The team’s biggest challenge was updating the MEP systems without sacrificing the historic details and spaces. Crews raised the second floor above the lobby to bring in contemporary MEP systems without interfering with the historic lobby space and its original groin ceiling and columns.

The tax-credit authorities also required the building to maintain its original 12-ft-high ceilings in the upper-floor corridors. To meet that requirement, all of the MEP systems had to be rerouted from above the hallway corridors and elevator lobbies during construction.

该团队在夹层层发现了一些原始的石膏架。工人重新制作了成型线,以将其扩展到整个水平。此外,该团队还重新创建了一家店面,该店面已变成电梯附近的新入口。

完整的九层结构设有76间酒店客房,各种聚会空间,咖啡吧,大厅,屋顶酒吧和60个座位的餐厅。

Crews completed 150,000 hours with no Occupational Safety and Health Administration recordable incidents and no lost-time accidents.