所有者/开发人员亚利桑那州立大学
General ContractorMcCarthy Building Cos.
Lead Design FirmZGF建筑师
结构KPFF咨询工程师
民事Dibble Engineering
MEP附属工程师
副建筑师BWS Architects


晚上9点之后2017年8月3日,在坦佩(Tempe)亚利桑那州立大学(Arizona State University)的顶级生物设计学院C上。从麦卡锡建筑物cos。筋疲力尽并被泥覆盖,大约有20群,拖到最近的酒吧,用一两杯啤酒放松身心。他们需要解压缩。他们刚刚花了四个小时从实验室大楼的地下室里救水。

五个小时前,高级项目经理布莱恩·库斯特(Bryan Kuster)坐在附近的办公室里,在听到风风ling叫声时,与两名项目经理一起经过分包商的变更命令。他冲到外面,看到远处的漏斗云。很快它开始像季风一样倒入。

“I looked at my weather app and it said 0% chance of rain,” says Kuster, McCarthy’s vice president for higher education operations.

Kuster去检查建筑物。水正在向下流入地下室,其中包含世界上第一个紧凑的X射线自由电子激光器。

野外工作人员被召回借给办公室工作人员一只手抬起头来。持续了四个小时。“这不是一场灾难;没有安装干墙。” Kuster说。

他补充说,联合危机的反应举例说明了麦卡锡的“全部”核心价值。该价值渗透到了该项目,该项目受到严格的预算,紧张的时间表和不断发展的计划的挑战。

ZGF Architects的执行合伙人泰德·海曼(Ted Hyman)说,即使是大学的不同群体,即功能,建筑和科学家,也可以合作,“有点哄骗。”

麦卡锡(McCarthy)在设计辅助方面签订了危险的建筑管理合同。Kuster将协作精神归功于准时交货和9700万美元的成本,在预算下为300万美元。在设计开发过程中设定的保证最高价格占原理图期间开发的估计值的0.6%。

Counting the basement, the lab is a five-level, 188,447-sq-ft building clad in copper. It will house the same number of principal investigators housed in both other labs, but in roughly 40% less space.

海曼说:“我们消除了中庭,大走廊,并优化了实验室的布局。”他补充说:“该建筑物是80%至90%的湿实验室”。

原始程序要求高于等级的三个级别。Hyman说,应所有者的要求,ZGF在原始信封内拟合第四级的预算。

The building, which is targeting LEED Platinum, is designed to use 44% less energy than the other campus labs. The team worked with the school to enact standards for reduced air-change rates. That in turn supported a chilled-beam hydronic system that decouples ventilation from cooling.

The most significant contributor to the building’s low-energy diet is the enhanced run-around loop energy recovery system (ERAL) in the air handlers, says Paul Erickson, a principal with consulting engineer, Affiliated Engineers Inc.

ERAL上的热水和冷水热交换器使空气处理程序中的三个线圈合并为一个。埃里克森说,线圈长度减小,这导致了一个小得多的机械阁楼。

排气气流中的蒸发冷却可为近半年提供足够的冷却效果,因此ERAL提供了所有必要的实验室化妆空气冷却,而无需使用校园冷水。

By partnering with a vendor capable of manufacturing the coils and packaging the controls—Konvekta U.S.A.—the complexities of a variable flow ERAL and other enhancements could be achieved with a much higher level of operational confidence, says Erickson.

The team is very proud of the laser lab, also known as a miniature accelerator, that is expected to revolutionize particle physics. The head of the lab, William Graves, was recruited from the Massachusetts Institute of Technology. The laser is designed to produce an X-ray beam similar to those produced by the very large accelerators at the national labs. The smaller laser will fit into any medical, scientific or industrial lab.


脱气

A big hitch: The laser lab, which requires the concrete basement walls to have zero magnetism, was added during design development. McCarthy figured that by degaussing the reinforcing steel to eliminate magnetism, instead of using more-expensive stainless steel rebar, there would be a savings of $1 million. The rebar degaussing process was intense and called for five measuring iterations.

下一个骄傲的物品是在广场上暴露的17个白色建筑混凝土柱。倾斜和直立的圆柱是麦卡锡的巨大头痛,这是自我渗透的混凝土工作。他们必须有尖锐的角落,没有口袋或蜂窝状。

为白色混凝土制定混合设计,振动技术和颜色,花了17个模型(两个全面)。该团队甚至拆除了一些测试列,这些测试列内置在适当的位置,这还不是snuff。

为了弥补专门用于列的额外时间,麦卡锡修改后的技术用于更典型的列,以使其更快地完成。

Beyond degaussing and other smaller measures, McCarthy shaved off roughly $1 million by modifying the original connection of the steel trusses that tie the copper envelope to the decks. And a savings of $800,000 came from eliminating basement chillers.

Another departure from the norm was that McCarthy held the contingency and released half to the owner when the structure topped out. That allowed the owner to make enhancements, such as adding a clean room.

Kuster说,最大的离职是整个团队的合作。他说,所有涉及的人都以信任和透明度的行动,并补充说:“那是巨大的。”


新利luckEnr最好的2018年最佳项目18luck官网