Gaylord Rockies Resort & Convention Center
Aurora, Colo.
Award of Merit

Owner:RIDA Development Corp.
Lead Design Firm:HKS Architects
General Contractor:Mortenson/WELBRO JV
Structural Engineer:Brockette Davis Drake
Civil Engineer:J3 Engineering Consultants Inc.
MEP Engineer:Blum Consulting Engineers Inc.
Lighting Design:Lang Lighting Design Inc.
Life Safety:Howe Engineers Inc.
Interior Design:Looney & Associates
Electrical Contractor:Encore Electric


During its 36-month construction period, the 1-million-sq-ft Gaylord Rockies Resort was the largest non-casino hotel being built in the U.S. Encore Electric installed more than 10,000 can lights and made more than 100,000 points with total station technology. Three 13.2-kva substations with 4,000 amps each serve the hotel’s electrical needs. Three equipment pump rooms provide service for water features, pools, a lazy river, the two-story slides and an infinity pool. The 75-ft-long LED television screen in the sports bar required an additional transformer and electrical panel just to power it.


Back to "Annual Awards Competition Attracts the Most Entries in Its History"