斯科茨代尔机场重建
Scottsdale, Ariz.
Best Project

Owner/Developer:Scottsdale Airport
Lead Design Firm:Mead & Hunt
General Contractor:JE Dunn Construction
Structural Engineer (business center):先进的结构工程
土木工程师:Trace Consulting
MEP, Structural Engineer (hangars):Mead & Hunt
Architecture:DWL Architects + Planners
Landscape Architect:洛根·辛普森(Logan Simpson)
Subcontractors:JB Steel; Bell Steel; Star Roofing; Suntec Concrete; Kovach Building Enclosures; Poole Fire Protection; Berg Drywall; Carlson Glass


The Aviation Business Center and executive hangars redevelopment at Scottsdale Airport consolidated the center’s administrative offices, customs operations and tenant spaces. A public plaza connects the 23,781-sq-ft center to the 30,000-sq-ft executive hangars. The aviation campus includes a restaurant, a break room and conference room.

新设施旨在使重建机场成为租户和周边社区的灯塔。进入航空业务中心后,雷鸟菲尔德二世退伍军人纪念馆(Stearman PT-17 Biplane)被悬挂在前入口附近。

斯科茨代尔机场于1942年首次成立,即美国进入第二次世界大战后不久,训练飞行员在天空中战斗。斯科茨代尔市(Scottsdale)于1966年收购了机场。

As is typical with airport construction, the need to maintain full airport operations as well as follow federal and municipal regulations challenged both the scheduling and execution of work. Everyone entering the jobsite was required to attend a safety orientation that included project-specific policies such as prohibiting access to unauthorized areas and maintaining a clean, organized jobsite so that tools and debris did not damage aircraft.

JE Dunn利用其国家质量团队来识别可能容易出现安装或功能困难的产品和设计组件。与设计团队讨论了这些项目,以便在收购之前找到解决方案。

Mock-ups were used to document the sequence of material installation and test systems for peak performance.

The contractor held pre-installation meetings with various trades to review contract documents, set quality expectations, assess the mock-ups and prepare for inspections and tests. Inspections were performed upon completion of the first piece of work to evaluate compliance and resolve issues before proceeding with subsequent tasks.

After completing each task, the contractor coordinated a pre-punch list with trades to verify quality and minimize closeout delays. The team also developed a plan to protect work put in place so that it wouldn’t get damaged as construction continued in other areas.

DWL Architects says the project is currently on track to achieve LEED Gold certification. The design of the Scottsdale Airport redevelopment takes advantage of a solar orientation strategically positioned to maximize views and daylight and minimize solar-heat gain.

航空商务中心的玻璃立面面向北部,整合的悬垂和阴影屏幕为南方和西部的暴露提供了额外的保护。

The building’s massing is subdivided into smaller elements and provides more protection for the glazing. The landscaping is punctuated by indigenous plants.