Planning

Connecticut

National Developmentis building Waterstone at the Stamford senior living facility. The up to $25-million project is expected to start in January 2020 and be completed in August 2021. The project includes demolishing a portion of an existing office building and constructing a 130-unit senior living facility for a total of 230,000 sq ft.National Development, 2310 Washington St., Newton Lower Falls, Mass., 02462-1449. DR#201800873796v4


Claremont Corp.是建立在萨默塞特Squa万豪酒店交流吗re. The up to $25-million project is slated to start January 2020. The project includes one four-story building above grade. The 129-room hotel will have 145 onsite parking spaces.Claremont Corp., 1 Lakeshore Center, Bridgewater, Mass., 02324-1407. DR#200800736770v26.


Maine

The Boys & Girls Club of Kennebec Valleyis building a $10-million facility on Pray Street in Gardiner. The timetable for construction on the 32,000-sq-ft building is unknown.Boys & Girls Club of Kennebec Valley, 14 Pray St., Gardiner, 04345. DR#201900869730.


The Yarmouth School Dept.is renovating and putting an addition on the Frank H. Harrison Middle School. The up to $15-million project includes an approximately 8,900-sq-ft, two-story steel-framed classroom addition. The project also includes reroofing a school facility and miscellaneous interior renovations to the existing school. Projects include associated mechanical, plumbing, sprinkler, electrical and sitework.Yarmouth School Dept., 101 McCartney St., Yarmouth, 04096-8155. DR#201800746140v11.


Massachusetts

MassDOT Highway Divisionis replacing the Lynn-Saugus Bridge. The more than $84-million project will replace the bridge that carries Route 107 (Salem Turnpike/Western Avenue) over the Saugus River. Bids are due at 2 p.m. on Jan. 28. Bidders must be prequalified by the Massachusetts Highway Dept. The project is expected to start in March 2020.MassDOT Highway Division, 10 Park Plaza-Transportation Building, Cashiers Office/Rm. 6261, Boston, 02116-3973. DR#200900460037v30.


The NE Farm Workers Council/Partners for Communityis redeveloping the Massasoit Block & Paramount Theater in Springfield. The up to $41-million project is expected to start in December and be completed in November 2020. The project includes an 81-room boutique hotel and performing arts center.NE Farm Workers Council/Partners for Community, 1628-1640 Main St., Springfield, 01103. DR#201700686995v5.


Bullfinch Cos.is building the 151 Taylor Street Distribution Facility in Littleton. The up to $50-million project includes a one-story building above grade totaling more than 144,000 sq ft. The project involves demolishing a two-story office building. The project has been granted planning board approvals, but a building permit has not yet been granted. Stantec is the architect.Bullfinch Cos., 250 1st Ave., Ste. 200, Needham, 02494-2814. DR#201800786127v5.


Rhode Island

Trinity Academy for the Performing Artsis planning a more than $11-million facility on Westminster Street in Providence that will include rehearsal and performance space, 19 classrooms, a film lab, a maker space, a dance and yoga studio and a shop for theater technology. Advancement of the design-bid-build project is pending approvals. The schedule has not yet been determined.三一学院表演艺术,150 Washington St., Providence, 02903. DR#201900856409v1.


On the Web

Much information forPulseis derived fromDodge Data & Analytics, the premier project information source in the construction industry. For more information on a project that has a Dodge Report (DR) number or for general information on Dodge products and services, call 1-800-393-6343 or visit the website atwww.dodgeleadcenter.com. To see an updated list of projects bidding in the New England region, visitenr.com//www.pjbjkak.com/newengland.