This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy.Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
Related Links: ENR's Superstorm Sandy Recovery Jersey Central Power & Light PSEG homepage Two of New Jersey's largest power utilities expect to spend at least $6.5 billion to protect systems from more severe weather after suffering massive damage last fall in Superstorm Sandy.Public Service Electric & Gas, Newark, has asked state regulators to approve a $3.9-billion infrastructure plan for electric and natural-gas systems and also plans to spend $1.5 billion on transmission in the next 10 years. Jersey Central Power & Light, part of First Energy, Akron, Ohio, has applied for a $2.6-billion block grant for storm hardening. "We must
Related Links: First $1.8B Leg of U.S. Offshore Wind Transmission Link Is Set Bechtel Tests the Wind for Great Lakes Alternative Energy Website of Chesapeake Climate Action Network, Takoma Park, Md. The third time could be the charm for Maryland Gov. Martin O'Malley's push to get state legislators to support a 200-MW offshore wind project. Passage of enabling legislation now appears likely as the primary statehouse opponent of two past efforts has exited a key committee.Two bills introduced in the House of Delegates and state Senate on Jan. 28 are substantially identical to legislation that was blocked in the Senate
Related Links: Feds Clear Path For Offshore Wind Offshore Support for Onshore Wind Website of Atlantic Wind Connection/NJ Energy Link The developer of what is touted as the first U.S. offshore wind energy transmission system, to run from Virginia to New York City, has picked Bechtel Group as EPC contractor for the first 189-mile, $1.8-billion leg off the New Jersey coast.Atlantic Wind Connection, a consortium led by internet giant Google, said construction would begin in early 2016 and be built in three phases over a decade. The first phase is to be in service in 2019. Alstom also was named
At least 300,000 people were without power along the US East Coast at mid-afternoon on Monday, Oct. 29 as rain and hurricane-force winds caused by Hurricane Sandy moved closer to shore causing outage totals to climb quickly.
EmberClear Corp., a Calgary, Alberta-based energy developer, said on Sept. 19 that it expects to begin construction on a 300-MW natural-gas-fired generation project west of Allentown, Pa.
Related Links: Groundwater Treatment Plant Sets Milestones at Hanford Nuclear Site Discovery of Cracks at Seabrook Nuclear Powerplant Generates Series of Tests The U.S. Dept. of Energy says that the transfer of 2,400 metric tons per year, or MTU, of natural uranium to the joint venture of Fluor Corp. and Babcock & Wilcox as payment for cleanup of a Cold War-era nuclear fuel plant in the Midwest would not adversely affect the domestic uranium industry. DOE's "bartering" approach has come under scrutiny by congressional appropriators; the U.S. Government Accountability Office has called for eliminating the companies as "sales agents" in
Related Links: ENR cover story on BE&K-1993 Theodore C. "Ted" Kennedy, who pushed non-union contracting to new arenas as CEO of BE&K Inc., but worked with organized labor and owners to boost construction safety, productivity, ethics and image, died May 8 in Birmingham, Ala. He was 81.The cause of death was post-surgery complications, says a spokesman for Kennedy.Kennedy was the son of a union ironworker and accompanied him to jobsites as the teenage "water boy," later earning an engineering degree from Duke University.He then espoused the open or "merit shop" labor approach in co-founding BE&K in 1972. After his co-founders
The Tennessee Valley Authority has added three years and $2 billion to its estimate to complete a partially built nuclear unit at its Watts Bar plant in Tennessee.
The Maryland Public Service Commission is moving ahead with a request for proposals for 1,500 MW of new gas-fired generation, despite concerns raised by its regional grid operator about power pricing impacts.
Photo courtesy of TVA Watts Bar plant unit 2, idle since 1988, is set for 2013 completion. In what it says is an effort to improve efficiency and eliminate confusing lines of authority and duplication of effort, the Tennessee Valley Authority has relieved Bechtel Corp., based in San Francisco, of construction-management duties at the $2.5-billion restart of unit 2 at TVA's Watts Bar nuclear powerplant.The federal power producer renegotiated its engineering, procurement and construction contract with Bechtel Power after the project's schedule slipped during the summer, says Terry Johnson, a TVA spokesman. “Fundamentally, we established a level of productivity, and