This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy.Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
Crossrail Ltd. attributes the latest delays to lower than planned productivity on work in shafts, portals and the 10 central section stations, exacerbated by workforce constraints caused by the pandemic.
Terry Morgan's ouster as chair of HS2 and Crossrail comes as the latter London tunnel line faces a new $2.5-billion budget hole and a likely finish beyond 2019.