This website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
This Website Uses Cookies By closing this message or continuing to use our site, you agree to our cookie policy.Learn MoreThis website requires certain cookies to work and uses other cookies to help you have the best experience. By visiting this website, certain cookies have already been set, which you may delete and block. By closing this message or continuing to use our site, you agree to the use of cookies. Visit our updatedprivacy and cookie policy to learn more.
Built to serve foster and community children and at-risk families in Chicago’s Roosevelt Square area, this 11,000-sq-ft community center was completed in just 13 months.
Despite initial concern that the project might be vulnerable to as much as $1 million in cost overruns, the two-phase, $36.5-million construction program was ultimately completed under budget thanks to innovative value engineering and negotiated change order requests.
After nearly eight years on hold, construction of the Arthur Capper Community Center in Washington, D.C., was ready to move forward—but with considerable changes.